PTS+ Application Manual

Penetrating Top Seal Plus - Application Guide

Step 1: Surface preparation

  • PTS+ is a coating. i.e. it's going to cover anything left on the surface to be treated.
  • So, ensure the surface is dry and clean.
  • Ensure the surface to be treated will not get wet for at least 24 hours after treatment. No rain, sprinklers etc.

Step 2: Applying PTS+

  • Use a hand-pump, Hudson can type sprayer for even, wetting, application.
  • Spray back and forth over the same area a minimum 2 to 3 times, overlapping as you move up to the adjoining dry area.
  • For vertical surfaces, apply from the bottom up.
  • For horizontal surfaces, apply from the low point, i.e. near a drain) up to the high point.
  • Apply until the surface stays wet for 5 to 10 seconds.
  • Spread any puddles remaining after 30 seconds with a mop or squeegee.
  • PTS+ can be applied to anything it does not bead up on.
  • It is impossible to apply a second coat of PTS+ over a previously PTS+ treated surface that has dried.

Step 3: Coverage

  • Coverage depends on the profile of the concrete surface. i.e. minute hills and valleys of exposed aggregate will require slightly more product than machine trowelled floors.
  • Expect 200 to 300 square feet per gallon with the average about 250 square feet per gallon.

Step 4: Curing Time

  • The surface treated with PTS+ will air cure in a few hours.
  • Do not walk on the wet surface before it air dries.
  • Do not allow any vehicular traffic for a minimum 24 hours.

Environmental and Safety Concerns

  • PTS+ contains zero VOCs, i.e. it is safe for the environment, animals and plants.
  • While safety goggles are not really required, rubber gloves are a good idea.

Clean up

  • Clean up hands and tools with soap and water.

Need Additional Help?

If you need additional assistance with PTS+ application or have specific questions, our team is here to help.

Contact Support